Update 7/18/08
De-Watering:
De-Watering started Friday July 11, 2008 in the marina basin. As of July 18 the basin has been pumped down to just a few feet of water remaining in the main channel ways. The Ohio Division of Wildlife was on site July 17, with the electric shock boat assisting in collecting and moving native fish from the marina basin into Lake Erie. Work continues with Ohio EPA and the US Army Corp of Engineers to assure compliance with permits. This next week, we will finish the dewatering and we are planning to start removing parts of the center peninsula. The north parcel is our first area to have marina materials placed upon it. As we begin the deepening and shaping of the marina basin large equipment will be moving across Fox Road and hroughout the construction zone. Please help us have a safe project. Drive and bike carefully throughout the area.
Lake Erie Water Snakes:
We have relocated 250 snakes so far during this project. We appreciate the effort of Kristen and Keith who keep us on track with this aspect of the project - protecting an endangered species.
Dock Construction:
The project construction bids submitted by various contractors were "opened" July 10, 2008. There were several bidders and it is encouraging to see the interest in the project. We hope to have the "low bidder" chosen this next week.
Next Open House: Scheduled for July 28, 2008 3:00Pm - 4:30PM Just on the south side of Aunt Erma's in the shade.
Thank you,
Scott Doty
Regional Manager
Lake Erie Islands state Park
The following Items are excerpts from previous updates that I felt some would find of value.
Reminders:
· Special note: The Construction Zone is considered anything within the Snake Fence . Please remain outside of the fenced area as required by safety regulations of construction sites.
· The contractor has put steel plates on Fox Road where they are crossing over the road. This will protect the roadway from the heavy equipment crossing it. There are 3 crossing areas; 1 by Aunt Erma's, Just North of Jim Roesch's former marina and next to St. Hazards.
· Signs warning of truck crossings. A few other safety barrels will be erected for safety. We ask everyone to remember to drive carefully through the construction zones & remind others as well.
· Lake Erie Water Snakes - LEWS Kristin has a full time LEWS specialist, Keith Hanson. Keith will be on the island working alongside the contractor checking snake traps and where the heavy equipment is working within the snake fenced area.
· Keith and Kristin will be relocating any snakes found within the area to areas outside the fenced construction zone. We welcome Keith to the project. If you see snakes with some colorful paint markings (blue or green). These are ones they have relocated.
· Several questions that seemed to be asked more frequently than some others were:
· The marina will be deepened to 10 feet of depth
· The project is still on track with the marina to be usable next summer
· The marina will have a design capacity of around 340 slips, we will be planning on starting dockage of close to 240 (includes the yacht club)
· Seasonal dockage will be a part of the marina dockage plan.
· We will plan another open house next month.